APRIL 4th 2011 TO APRIL 25th 2011
LOCATION: |
DESCRIPTION OF WORK |
|
100th to 99th Streets |
Set up Rebar Fabrication Yard. Con Edison pulling & splicing cables. Excavate for 60" water main tie-in at 99th St. |
|
99th to 97th Streets |
Excavate and install 60" watermain tie-in. Installation of support piles for sewer. Con Edison pulling and splicing cables |
|
97th to 96th Streets |
Install 48" sewer crossing and temporary connection. Restore sidewalk, 2nd Ave west side between 96th and 97th.
|
|
96th to 95th Streets |
Install Geo Technical instrumentation. Installations support for deck beams. Excavate and install deck beam footings. Install 36" water main. |
|
95th to 94th Streets |
Installation of tie in for 36" water main. |
|
94th to 93rd Streets |
Removal of existing support structures for preparation of foundation work at Ancillary # 1 (93rd St). |
|
93rd to 92nd Street
|
Continuing with rock removal from Launch Box. Operation of vertical conveyor. |
|
92nd to 91st Streets
|
Tunnel Boring Machine excavating East Tunnel. TBM currently on 2nd Avenue between 90th and 91St |
|
91st to 90th Streets
|
Dismantling and removing ground freeze plant and equipment.
|
|
88th to 87th Streets |
Work zone located on West side of 2nd Ave. Excavating & installing 12" Water Main
|
|
87th to 86th Streets
|
Work
zone located on West side of 2nd Ave. Completion of Con Ed Duct
work. |
|
86th to 85th Streets
|
Work zone located on West side of 2nd Ave. Excavating & installing 12" water main and Con Edison duct run. Con Ed splice and energize North East area |
|
85th to 84th Streets
|
Maintenance and Protection of Traffic - Contractor material storage area Con Ed install cables North West location |
|
84th to 83rd Streets |
West Side: Continue support of excavation installation. Mechanical excavation of rock. DOT permit for closure of 83rd St between 1st & 2nd and between 2nd & 3rd Aves between 9am and 5pm Monday thru Friday. Continue with electric conduit and manhole installations. Con Ed cable splicing |
|
83rd to 82nd Streets |
Maintenance and Protection of Traffic- Contractor material storage area. Con Edison cable splicing |
|
79th to 78th Streets |
Center Maintenance and Protection of Traffic. |
|
74th to 73rd Streets |
Operation of water treatment plant |
|
73rd to 72nd Streets |
Continuing controlled blasting activities on 2nd Avenue. Demobilization of the crane. Start construction of muck conveyance system.
|
|
72nd Street North West Side |
Continuing interior abatement/ demolition of 259 E 72nd St Ancillary 2. Installation of Support of Excavation for East/South Wall. Gas and electrical utility relocation. |
|
72nd to 71st Streets
|
Contractor storage and maintenance area |
|
71st to 70th Streets |
Complete utility connections and build stairs to employee trailers. Ready trailers for employee use mid to end April |
|
70th to 69th Street |
Continuing of controlled blasting activities on 2nd Avenue. Installation of instrumentation to 63rd Street |
|
69th Street North West Side |
Gas and electrical utility relocations. Preparation for Asbestos abatement. |
|
3rd Ave between 62nd and 63rd Street |
Removal of bus shelter and elimination of M 102,103,104 bus stop at the south east corner of 63rd St. Installation of Geo-tech instrumentation. |
|
3rd Ave. between 63rd and 64th Street |
Installation of Maintenance and protection of traffic on east side of 3rd Avenue. No parking permitted traffic reduced to 5 lanes |
BE ADVISED: Con Ed, Empire City Subway and Verizon may be performing cable and gas line work outside regular SAS construction Hours. Some of this work will take place on 2nd Ave between 68th and 74th Streets will be intermittently carried out in support of the Second Avenue Subway
Work Hours:
7:00 AM to 10:00 PM, Monday through Friday
10:00 AM to 7:00 PM Saturday.
Work Taking Place under Decking is Permitted 24 Hours.
If you have additional questions, please contact Claudia Wilson at (212) 792-9716 from 9:00AM to 5:00PM Monday through Friday, or contact the 2nd Avenue Subway Hotline 24 hours/7 days a week at (646)252-2670.
Traffic Update
100th Street to 95th Street
- Four lanes of traffic are on the EAST SIDE of Second Ave
- Work zone will be set up on the WEST SIDE of Second Ave
- The West side work zone will be approximately 40 Foot wide, plus 7 Foot sidewalk
- No Standing at Anytime on the West side of Second Ave 95th Street to 101st Street
- No Standing on the East side 7AM-10AM and 4PM-7PM Monday-Friday
- No Standing on East side 10AM-4PM, EXCEPT Trucks Loading and Unloading
91st Street to 95th Street
- Four lanes of traffic currently on WEST Side of 2nd Avenue
- Work zone is set up on the EAST SIDE of 2nd Avenue
- The EAST SIDE work zone will be approximately 40 FOOT wide, plus 7' sidewalk
- No Standing at anytime on the EAST SIDE of Second Ave 91st Street to 96th Street
- No Standing on the WEST SIDE 7AM-10AM and 4PM-7PM Monday-Friday except truck loading or unloading
- Parking ALLOWED on WEST SIDE 7PM-7AM Weekdays and all day Saturday and Sunday
88th Street to 82nd Street
- Four lanes of traffic South of 85th St. will be moved to the West Side of Second Ave
- Work zone will be set up on the East Side of Second Ave South of 85th St.
- The East Side work zone will be approximately 40 Foot wide, plus 7 Foot sidewalk
- No Standing at Anytime on the East Side of Second Ave 87th Street to 82nd Street
- No Standing at Anytime on the West Side of Second Avenue 87th to 86th Streets
- No Standing on West Side 10AM-4PM, EXCEPT Trucks Loading and Unloading
74th Street to 68th Street
- Work zone is set up on the EAST SIDE of Second Ave
- The EAST SIDE work zone will be approximately 40 FOOT wide, plus 7' sidewalk
- No Standing at anytime on the EAST SIDE of Second Ave
- No Standing on the WEST SIDE 7AM-10AM and 4PM-7PM Monday-Friday
- No Standing on WEST SIDE 10 AM-4PM, EXCEPT trucks loading and unloading
- Parking ALLOWED on WEST SIDE 7PM-7AM Weekdays and all day Saturday & Sunday
- No Parking on East or West Sides of Second Ave between 78th and 79th Streets
NOTIFICATION OF CONTROLLED BLASTING ACTIVITY
69th to 73rd Streets
The Second Avenue Subway project will be using a well established excavation technique called controlled blasting to excavate two access shafts at 69th Street and 72nd Street which will eventually be used as access points for the construction of the 72nd Street Station. We have used this technique at many of our projects in Manhattan.
Controlled blasting activities are scheduled to begin on or about February 8th, 2010.
The Fire Department of New York (FDNY) has approved a controlled blasting plan for the area of Second Avenue between 69th and 73rd Street which will be carried out in coordination with the MTA and S3 Tunnel Constructors. All blasting will be conducted under the direction and regulations of the FDNY. Blasting is permitted to take place during the approved Second Ave Subway working hours of 7 AM to 10 PM, although, every effort will be made to limit blasting to daylight hours.
Blasting Procedures
- All pedestrian and vehicle traffic will be temporarily stopped during each blast occurrence. Blasting will occur approximately 4 to 5 times daily, with each blast lasting no more than one minute.
- There will be a warning whistle before each blast
- 1 whistle as a warning sound
- 2 whistles indicate the blast is imminent
- 3 whistles indicate the blast is complete and all is clear.
- Flagging personnel will be positioned at the north, south, east and west corners of the blast zone to inform and direct pedestrians.
- Signs will be posted around the work site that will state: DANGER BLASTING- NO RADIO TRANSMITTING
As required by New York State regulations, and monitored by FDNY, all explosive materials are delivered to and from the work site daily. Vibration and noise limits have been established by the MTA and the project designer. The vibration and noise readings will be monitored by the construction management team.
Please direct any questions or concerns to Marcus Book, Assistant Director, MTA NYC Transit Government and Community Relations at 646-252-2675 or Claudia Wilson at the work site at 212-792-9716.
If you have additional questions, please visit the Keeping in Touch page for contact information.| Project History | Project Description |